Can I set an automatic due date in advance?

Options
Kim Albech Sorensen
Kim Albech Sorensen EN Pro Posts: 2 Beginner
edited August 2023 in Ask the Community

Can I set an automatic due date - like 1 week forward - on new tasks created in a certain section of a project

Tagged:

Best Answer

  • Joerg Koper
    Joerg Koper DACH Partner, MT Tester, DE Business, EN Advocate Posts: 1,386 Community Leader
    edited August 2023 Answer ✓
    Options

    Hi @kimas and welcome to the community 👋🙂

    I'm not sure what exactly you mean, but you can set an automation for the task due date with the desired days, let's say seven days, until the due date.

    Whenever you create a new task in a section with this automation enabled, the task will get a due date of seven days. Even a task, that is moved into the section, will get the set due date.

    I hope, that's what you were looking for.

    Best, Jörg